May 2026

Updates on the development

July 2026

Lindum Homes update:

• First 3 plots fronting Nettleham Rd have been released for sale. The fourth plot on the frontage will be the show home, which will open in september. 

https://lindumhomes.co.uk/developments/west-thorne-grange-new-homes-for-sale-in-scothern-lincoln-ln2-2tz/

• A lot of activity planned for July, specifically the attenuation tank being installed. This will see a crane on site for next 4 weeks, with the tank being transported onto site in sections and assembles in situ. 

• The generator is needed to power the site, as we need to drop the overhead cables to get the power live, and this is going through a legal process. This is unlikely to be concluded until the end of summer.

________________________________________________________________________________________________________________________

May 2026

Progress is now going very well, as we progress the first four (frontage to Nettleham Road Plots 1 - 4) houses in to build. We hope to open the show home/sales on site in July this year, with the first people moving in by the end of the year.

 

Prior to that, it will be a busy summer with onsite infrastructure, key things include (and dates subject to usual caveats).

 

Installation and connection of the onsite electricity substation by mid-June

• Dropping the overhead cables that cross the site and re-routing underground late June/early July

• Installation of the attenuation tank in June/July

• Installation of the surface water and foul water pump station July/August.

So all in all, a lot going on but, by the end of the summer, the tank will be in, and the site will have its own services.

 

aerial view

Published: Thursday, 2nd July 2026